Southern Natural Gas Company
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/22/2004, Docket: RP04-494-000, Status: Effective
Third Revised Sheet No. 216 Third Revised Sheet No. 216 : Effective
Superseding: Second Revised Sheet No. 216
GENERAL TERMS AND CONDITIONS
(Continued)
3. Date service is requested to commence: ______________________________
Date service is requested to terminate (for FT or FT-NN Service):________________
To be a considered a valid request, IT service must be requested to begin within
90 days of the date of the request and firm transportation service must be requested
to begin within 60 days of the date of the request, except if the request involves the
construction of facilities or the issuance of any necessary certificate authorization
to Southern, or is part of an open season under Section 2.1(b)(iii) of these General Terms
and Conditions.