Southern Natural Gas Company
Seventh Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2005, Docket: RP04-523-000, Status: Effective
Original Sheet No. 212I.07A Original Sheet No. 212I.07A : Effective
41.3(c) (cont.)
(4) percent of the daily quantities delivered by COMPANY at the
Delivery Point, the group level, or the operator level,
respectively, then the scheduling penalty shall not be assessed
hereunder. Subject to the provisions of Section 41.3(d) below,
the scheduling penalty shall be equal to the maximum
Transportation Charge under the IT Rate Schedule multiplied by the
quantities in excess of the allowed variance, provided, however,
that such penalty shall be waived for an interruptible SHIPPER
whose scheduled volumes are bumped by a firm intra-day nomination
but shall be waived only for the day that such bumping occurs.
(d) If COMPANY has given notice that it is assessing one of the
foregoing scheduling penalties under Section 41.3(b) or (c) at a
Receipt or Delivery Point on a day when it is also limiting
receipts or deliveries at such point, then COMPANY shall so specify
in its notice. The scheduling penalty assessed on any such day
shall be equal to $15.00 per Dth multiplied by the quantities in
excess of the allowed variance under the applicable provision
above.