17.10 New Measurement Techniques


If at any time a new method or technique is developed

with respect to gas measurement or the determination of the

factors used in such gas measurement, such new method or

technique may be substituted by mutual agreement between VGS

and the interconnecting Operator.


17.11 Failure of Metering Equipment


If, for any reason, any measurement equipment is (i)

out of adjustment, (ii) out of service, or (iii) out of

repair and the total calculated hourly flow rate through

each meter run is found to be in error by an amount of the

magnitude described in Section 17.6 above, the total

quantity of gas delivered shall be redetermined according to

the first of the following methods that is feasible:


a. by using the registration of any check

metering facility, if installed and

accurately registering (subject to

testing as described in Section 17.4



b. by correcting the error by re-reading of

the official records, or by

straightforward application of a

correction factor to the quantities

recorded for the period (if the net

percentage of error is ascertainable by

calibration, tests or mathematical



c. by using the registration of telemetry

equipment connected to VGS' or Operator's

metering facilities, if installed and

accurately registering;