Venice Gathering System, L. L. C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2005, Docket: RP05-430-000, Status: Effective
Second Revised Sheet No. 104 Second Revised Sheet No. 104 : Effective
Superseding: First Revised Sheet No. 104
GENERAL TERMS AND CONDITIONS
(Continued)
b. VGS will support the following allocation methodology types at all
points: Ranked, Pro Rata, Percentage, Swing, and operator provided
value. VGS will not limit the number of PDA allocation
methodologies that may be used during an allocation period. A new
PDA may be required when a nomination changes; provided, however,
a PDA for a partial Day will not be permitted if it would result
in a change in quantities allocated for flow prior to submittal of
the new PDA. If an OBA is in effect at a point, a PDA is not
required to be submitted. VGS will post on its Internet Home Page
those Point(s) of Receipt and Delivery where an OBA is in effect.
c. VGS will report daily operational allocations within one business
day after the end of the gas day in which gas has flowed. If the
best available data for reporting daily operational allocations is
the scheduled quantity, VGS will use the scheduled quantity for
the daily operational allocation.
This standard applies to the daily provision of operational
allocated quantities whether they are provided pursuant to NAESB
WGQ Standard 2.4.3 or NAESB WGQ Standard 2.4.4.
Upon request to VGS, a Service Requester (SR) will be provided
operational allocated quantities pursuant to NAESB WGQ Standard
2.4.3 or 2.4.4 for the transaction(s) that have been scheduled by
VGS for the SR.
VGS can agree to send the operational allocated quantities on a
daily basis to a SR rather than accept the Upload of Request for
Download for operational allocated quantities.
VGS is not required to support requests for operational allocated
quantities other than on an "all locations for an SR basis."
Where VGS has determined to support this standard in a manner
other than:
a) providing specific operational allocated quantities in
response to a request for same, or
b) providing operational allocated quantities on an "all
locations for an SR basis," then the SR can rely on the
absence of a line item(s) provided by VGS as indicative that
the particular line item(s)' scheduled quantities are
operational allocated quantities.