Venice Gathering System, L. L. C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/01/1999, Docket: RP99-376-000, Status: Effective

First Revised Sheet No. 90 First Revised Sheet No. 90 : Effective

Superseding: Original Sheet No. 90

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

6.18 Quick Response For Nominations Outside Timely/Intra-day

Nomination Schedule

 

a. With the exception of otherwise stated GISB nominations deadlines,

when VGS receives a Nomination document from a Service Requester

by the conclusion of a given quarter hour period, VGS will send

to the Service Requester's designated site a corresponding Quick

Response document by the conclusion of the subsequent quarter hour

period.

 

b. VGS's nightly processing and routine maintenance occurring

outside of normal business hours are apt to interrupt the normal

schedule for nominations/quick response turnaround stated in GISB

Standard 1.3.37. Such delays should be kept to a minimum. The

normal schedule should be resumed at the earliest opportunity

and no later than the start of normal working hours the following

day, seven days per week.

 

6.19 Confirmation Quick Response Outside Timely/Intra-day

Nomination Schedule

 

a. When a confirmation Requester receives a Confirmation Response

document from a Confirming Party by the conclusion of a given

quarter hour period, the Confirmation Requester will send to the

Confirming Party's designated site a corresponding Confirmation

Response Quick Response document by the conclusion of the

subsequent quarter hour period.

 

The quarter hour periods will be defined to begin on the hour and

at 15, 30, and 45 minutes past the hour. A given quarter hour will

contain all transactions whose receipt time is less than the

beginning of the subsequent quarter hour.

 

b. Confirming Parties' nightly processing and routine maintenance

occurring outside of normal business hours are apt to interrupt

the normal schedule for confirmations/quick response turnaround

stated in GISB Standard 1.3.45. Such delays should be kept to a

minimum. The normal schedule should be resumed at the earliest

opportunity and no later than the start of normal working hours

the following day, seven days per week.

 

7. RESERVED FOR FUTURE USE