Venice Gathering System, L. L. C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 01/01/1998, Docket: CP97-533-002, Status: Effective

Original Sheet No. 66 Original Sheet No. 66 : Effective






3.4 Request Invalidation


Requests for interruptible service under this FERC

Gas Tariff will be invalid and will not be considered if

service is requested to commence later than six (6) months

after the information specified in Section 5 of the General

Terms and Conditions is provided to VGS.


3.5 Execution of Service Agreement


Shipper must execute an Interruptible Service

Agreement in the form contained in this FERC Gas Tariff

within thirty (30) days from the date VGS tenders an

Interruptible Service Agreement for execution. If a Shipper

fails to execute an Interruptible Service Agreement within

thirty (30) days, the request for interruptible service

shall be deemed a nullity for all present and future



3.6 Requests For Operating Data


Upon request of VGS, Shipper shall submit estimates

of daily, monthly and annual quantities of gas to be

transported, including peak day requirements, together with

the estimated amounts thereof applicable to each Receipt

Point and Delivery Point. VGS shall use such information

and operating data to determine to the extent practicable

its System's Available Capacity, to evaluate potential

System capacity needs, to plan its maintenance and repair

operations, and to assure adequate service to its Shippers.