Freebird Gas Storage, L.L.C.
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2008, Docket: RP08-304-000, Status: Effective
Original Sheet No. 30 Original Sheet No. 30 : Suspended
2.2 Gas which is scheduled for daily injection or withdrawal under this Rate
Schedule is subject to interruption based upon changes in Firm storage service
nominations received by Freebird or when necessary to maintain the operational
integrity of Freebird’s System. Prior notice of interruption will be given
pursuant to Section 5 of the General Terms and Conditions of this FERC Gas
Tariff. In the event that Freebird notifies the Shipper of an interruption in
service under this Rate Schedule, the Shipper must cease injections or
withdrawals, in whole or in part, as specified by
Freebird.
2.3 To the extent storage capacity which is being utilized by an Interruptible
Shipper hereunder is needed by Freebird in order to satisfy Freebird’s Firm
service obligations or such capacity is otherwise necessary to avoid adverse
impact on the operation of Freebird’s System, Freebird may require Shipper to
withdraw all, or any portion of, the Park Balance held in storage by Freebird
under this Rate Schedule for the account of Shipper. Freebird will notify the
Shipper of the need to withdraw Gas and the quantity to be withdrawn, and
shall specify the time period in which the Shipper must comply with the
notice. Freebird’s notice to Shipper may be given orally, but shall be
confirmed in writing via U.S. mail, e-mail, instant messaging or facsimile to
the Shipper. Unless Freebird otherwise agrees, Shipper shall be required to
make nominations ratably over the specified time period. During the period
specified by Freebird for withdrawal, Shipper may negotiate a sale in place of
its Gas in storage to another Shipper with storage capacity available under
one of Freebird’s Rate Schedules pursuant to Section 18 of this FERC Gas
Tariff. If Shipper fails to withdraw or sell in place such Park Balance
within the time period specified by Freebird, then Freebird may take, free and
clear of any adverse title, claims or liens, title to such IPS Park Balance as
Shipper was instructed to withdraw, at a price per Dth equal to the Current
Market Price (as defined in Section 8 below), less Freebird's costs related to
Shipper’s failure to timely remove its Gas, and Freebird shall credit such
proceeds to any amount owed by Shipper to Freebird; provided, however, that
for each Day Freebird is unable to schedule the withdrawal of Shipper’s Gas,
the period specified for withdrawal shall be extended by a corresponding number
of Days.
3. OVERRUN SERVICE
3.1 Provided it can be accomplished by Freebird without detriment to
Freebird’s System and Freebird has injection capacity available, Freebird may,
upon request of Shipper and after confirmation by Shipper’s Transporter,
schedule and inject on an Interruptible basis quantities of Gas in excess of
Shipper’s MDIQ, provided that Shipper’s Interruptible Park Balance has not
exceeded Shipper’s MPQ. Such Overrun Quantities shall be subject to the
charge set forth in Section 4(d) of this Rate Schedule.
3.2 Provided it can be accomplished by Freebird without detriment to
Freebird’s System and Freebird has withdrawal capacity available, Freebird
may, upon request of Shipper and after confirmation by Shipper’s Transporter,
schedule and withdraw on an Interruptible basis quantities of Gas in excess of
Shipper’s MDWQ, provided that Shipper has a quantity of Gas in Shipper’s
Interruptible Park Balance not less than the quantities Shipper shall have
nominated for withdrawal on such Day. Such Overrun Quantities shall be
subject to the charge set forth in Section 4(e) of this Rate Schedule.
3.3 Freebird shall have the right to interrupt or not to schedule all or part
of the Overrun Quantities nominated, subject to Section 5 of the General Terms
and Conditions of this FERC Gas Tariff, in which event Freebird shall notify
Shipper.