Mogas Pipeline LLC (Fomerly Missouri Interstate Gas)
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2008, Docket: CP06-407-002, Status: Effective
Original Sheet No. 13 Original Sheet No. 13 : Pending
RATE SCHEDULE FT
FIRM TRANSPORTATION SERVICE
(Continued)
4. Monthly Bill
The Monthly Bill for FT service shall be equal to:
(a) Reservation Charge: A reservation rate determined
under Section 3.1 of this Rate Schedule multiplied by the
Shipper's MDQ established in the FT Agreement;
(b) Commodity Charge: The applicable commodity rate
under Section 3.1 of this Rate Schedule multiplied by the
dekatherms of gas transported and delivered pursuant to this Rate
Schedule in the month. The Commodity Charge shall be set forth
in the FT Agreement and shall be no more than the maximum nor no
less than the minimum commodity rate specified for FT Service in
the Schedule of Rates for Transportation.
(c) Authorized Overrun Service Charge: A charge equal
to the product of the applicable authorized overrun rate and any
authorized overrun quantities permitted by Transporter during the
billing month; and
(d) Other Fees and Charges: Any other fees and charges
applicable pursuant to Section 3 of this Rate Schedule.
5. Receipts and Deliveries
5.1 Transporter shall not be required to receive gas at
the Receipt Point if the Shipper has failed to make and properly
implement all necessary arrangements on upstream pipelines.
5.2 Transporter shall not be required to deliver gas at
the Delivery Point if Shipper has failed to make and properly
implement all necessary arrangements on downstream pipelines or
distribution companies.
6. Waiver
Transporter may waive any rights hereunder or any obligations of
Shipper hereunder on a basis that is not unduly discriminatory;
provided that no waiver shall operate or be construed as a waiver
of other or future rights or obligations, whether of a like or
different character.