Mississippi Canyon Gas Pipeline, LLC

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/20/1998, Docket: CP96-159-006, Status: Effective

Original Sheet No.141 Original Sheet No.141 : Effective

 

GENERAL TERMS AND CONDITIONS (cont'd)

 

 

20.6 Transporter shall submit an invoice to the requesting

Shipper in the amount of the new facilities cost.

Shipper shall make payment to Transporter pursuant to

the provisions of Section 14.2 of these General Terms &

Conditions.

 

20.7 Transporter shall commence to construct and install the

requested facilities or modify existing facilities upon

receipt of the payment pursuant to Section 20.6.

 

20.8 Within ninety (90) days after commencing service for

the requesting Shipper, Transporter shall determine the

actual cost of constructing and installing the

requested facilities. If the above cost is less than

the new facilities cost paid by the requesting Shipper

under Section 20.6, the difference shall be refunded to

the requesting Shipper within thirty (30) days of such

determination.

 

20.9 Transporter shall have title to, own and operate all

new facilities added to its system pursuant to this

Section 20.