11.2 Adjusting Nominations - (b)(ii) (cont'd)
Primary and Secondary Receipt and Delivery
Points is not in excess of the MDQ under
Shipper's FT-1 or FT-2 Transportation
Service Agreements multiplied by the
Shipper Specific Heating Value.
(iii) Transportation service at other
Secondary Receipt and Delivery Points up to
the remaining available capacity of each
point to the extent that the summation of
Shipper's nominations at Primary and
Secondary Receipt and Delivery Points is
not in excess of the MDQ under Shipper's FT-
1 or FT-2 Transportation Service Agreements
multiplied by the Shipper Specific Heating
Value.
(iv) Transportation service according to the
applicable rate for quantities nominated
under an IT-1 Transportation Service
Agreement, such that Shippers who pay
higher rates are curtailed after those who
pay lower rates.
(v) Imbalance make-up nominations
(vi) Valid MDQ make-up nominations under FT-1 &
FT-2 Transportation Service Agreements
(c) If, on any day, Transporter determines that
the capacity of its system, or any portion
thereof, including Receipt and Delivery
Points, but excluding any restraints of
upstream and/or downstream pipelines, is
insufficient to provide all service
requirements which are nominated to receive
service on such day, then the following
curtailment policy, which could result in
curtailment of service, to zero if necessary,
will apply:
(i) If the above determination of constraint
is made BEFORE Scheduled Quantities are
determined for the constrained Receipt
and/or Delivery Point(s), then
adjustments to nominations shall be made
pursuant to subsection 11.2(b), thereby
resulting in allocations of available
capacity to higher priority services