RATE SCHEDULE FT-2
FIRM TRANSPORTATION SERVICE (cont'd)
10. GAS PRODUCTION FORECAST UPDATES (cont'd)
10.2 Additional Updates (cont'd)
(iii) increase or decrease its MDQ, including a permanent reduction pursuant
to Section 7, then Transporter shall have the right to request an updated gas
production forecast from Shippers, subject to the provisions of Section 10.1.
Shipper shall provide such information, provided Transporter shall not require
such updates more often than two times within any calendar year, inclusive of
the annual update required in Section 10.1.
10.3 Technical Data
Transporter may request supporting technical data from Shipper to substantiate
gas production forecasts supplied in Sections 10.1 or 10.2. Shipper shall
supply such supporting technical data on a confidential basis. Transporter
will review the technical data to evaluate the reasonableness of Shipper's
proposed MDQs.
10.4 Changes to MDQ
Shipper's MDQs may be increased based on the updated production profile only
to the extent firm capacity is available and not previously committed to
another Shipper, in accordance with Section 6.5.
If the updated gas production forecast does not support a Shipper's previous
MDQ profile, then Shipper will be required to submit a Service Request Form
to amend Exhibit A of the FT-2 Transportation Service Agreement to conform
its MDQs to the updated gas production forecasts effective the next available
Delivery Period after six months notice, as provided in Section 6.2(a).
10.5 Third Party Analysis
If in Transporter's judgment the updated gas production forecast and
associated MDQs provided in Sections 10.1 or 10.2 are not reasonable, then
Transporter shall meet with Shipper to review any technical data that is the
basis for the updated gas production forecast.
Transporter and Shipper shall make a good faith attempt to concur on an
updated gas production forecast. If the parties cannot reach agreement on
the updated gas production forecast and the associated MDQs, then the
technical data provided by Shipper shall be supplied to a mutually
acceptable and technically competent third party on a confidential basis
to develop an updated gas production forecast, which will be utilized by
Transporter.
Shipper will be required to submit a Service Request Form to amend Exhibit
A of its FT-2 Rate Schedule to reflect the MDQs supported by the third party
analysis to the extent capacity is available. Shipper and Transporter will
share all third party costs equally.