Mississippi Canyon Gas Pipeline, LLC

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/20/1998, Docket: CP96-159-006, Status: Effective

Original Sheet No.18 Original Sheet No.18 : Effective

 

RATE SCHEDULE FT-2

FIRM TRANSPORTATION SERVICE (cont'd)

 

 

2.3 Transporter shall not be required to install,

operate or maintain any additional facilities in order

to provide transportation service under this Rate

Schedule. However, if Shipper agrees to a New

Facilities Charge which will allow Transporter to

provide the transportation service(s) requested by the

Shipper, then Transporter shall install and operate the

new facilities if such facilities do not adversely

affect Transporter from providing transportation

services under then existing Transportation Service

Agreements subject to the receipt of all necessary

regulatory authorizations. A New Facilities Charge

shall not apply to any of Transporter's Facility

constructed pursuant to the certificate issued in

Docket No. CP96-159-000.

 

2.4 Service under this Rate Schedule shall be

nominated in accordance with the procedures set forth

in Section 11 of Transporter's General Terms and

Conditions.

 

2.5 Capacity available for firm transportation

shall be allocated among Shippers receiving

service under Rate Schedules FT-1 and FT-2 in

accordance with Section 11 of the General Terms

and Conditions of Transporter's FERC Gas Tariff.

 

3. DELIVERY AND RECEIPT POINTS, PRESSURES, UNIFORM QUANTITIES

 

3.1 Receipt Points: The Primary Receipt Point(s) on

Transporter's Facility shall be specified on Exhibit

"A" to the FT-2 Transportation Service Agreement.

 

3.2 Delivery Points: The Primary Delivery Point(s) on

Transporter's Facility shall be specified on Exhibit

"A" to the FT-2 Transportation Service Agreement.

 

3.3 Pressures: Shipper shall deliver gas to

Transporter at the pressure required from time to time

to enable the gas to enter Transporter's Facility at

the Receipt Point(s). Transporter shall operate

Transporter's Facility at a pressure sufficient to

deliver all quantities of gas which are scheduled to be

delivered at the Venice Gas Plant Delivery Point. In

no event shall Transporter be required to install