Sea Robin Pipeline Company, LLC
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/31/2004, Docket: RP05- 87-000, Status: Effective
Original Sheet No. 185 Original Sheet No. 185 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
17. FORCE MAJEURE (Continued)
party, however, shall not relieve it of liability in the event
of its negligence or in the event of its failure to use
reasonable diligence to remedy the situation and remove the
cause in an adequate manner and with all reasonable dispatch,
nor shall such causes or contingencies relieve either party of
liability otherwise unless such party shall give notice and
full particulars of the same in writing or by telephone or, in
the case of Sea Robin, on Messenger to the other party as soon
as possible after the occurrence relied on.