Sea Robin Pipeline Company, LLC

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/31/2004, Docket: RP05- 87-000, Status: Effective

Original Sheet No. 109 Original Sheet No. 109 : Effective

 

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

 

2. REQUESTS FOR SERVICE (Continued)

 

additional information in a specific case if necessary, in

Sea Robin's reasonable judgment, to substantiate the data

provided.

 

(b) To be a valid request, the service requested under Rate

Schedule FTS-2 must commence within twelve (12) months of

the Valid Date, except where the service requires the

construction of facilities to provide the service and/or

receipt of regulatory approvals from the FERC or other

regulatory agency; provided, however, Sea Robin shall not be

required to make available firm capacity to Shipper until

the requested commence date.

 

(c) Sea Robin shall notify a Shipper whose request for service

under Rate Schedule FTS or ITS is rejected because of

failure to submit or substantiate all data specified by

Sections 2.2 and 2.10 herein or whose request fails to

comply with any other terms of this Tariff within two (2)

business days after receipt of Shipper's request and shall

state the reasons therefore. Sea Robin shall also promptly

notify Shipper if it cannot satisfy an otherwise valid

request due to lack of capacity.

 

2.4 Within two (2) Business Days of Sea Robin's decision to accept a

request for service under Rate Schedule FTS or ITS, Sea Robin

shall notify Shipper that its request for service is accepted

and shall tender a Service Agreement to Shipper for execution.

 

2.5 For a request for service under Rate Schedule FTS-2, Sea Robin

may take up to thirty (30) days after receipt of all information

to be provided by Shipper, including, but not limited to, the

production profile and technical data contained in Section 4.1

of Rate Schedule FTS-2, or up to thirty (30) days after

conclusion of an open season described in Section 10.5 herein,

assuming all the necessary information has been received, to

evaluate Shipper's request. Within five (5) Business Days of

Sea Robin's decision to accept a request for service, Sea Robin

shall notify Shipper that its request for service is accepted

and shall tender an FTS-2 Agreement and a Reserve Commitment

Agreement to Shipper for execution. No service under Rate