Sea Robin Pipeline Company, LLC
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2007, Docket: RP07-683-000, Status: Effective
First Revised Sheet No. 44 First Revised Sheet No. 44 : Effective
Superseding: Original Sheet No. 44
RATE SCHEDULE ITS
INTERRUPTIBLE TRANSPORTATION SERVICE
(Continued)
(e) If Sea Robin determines that Shipper has failed to provide
adequate assurance of Shipper's solvency and ability to
perform and Shipper refuses to post security in
an amount equal to three months billing assuming full
contract quantities in accordance with Section 15.2 of the
General Terms and Conditions;
(f) Unless and until Shipper provides Sea Robin with acceptable
evidence that all applicable regulatory requirements can be
met;
(g) If Shipper is unwilling to pay the maximum rate applicable
to such service under this Rate Schedule ITS;
(h) If such service does not comply with Sea Robin's General
Terms and Conditions, this Rate Schedule ITS or the ITS
Agreement;
(i) If the ITS Agreement has expired; or
(j) Which would cause a reduction in Sea Robin's capacity
disproportionate to the service requested (without regard
to distance).
2. APPLICABILITY AND CHARACTER OF SERVICE
2.1 The transportation services provided under this Rate Schedule
ITS shall be performed under Subparts B and G of Part 284 of
the Federal Energy Regulatory Commission's (Commission)
Regulations. This Rate Schedule ITS shall apply to all gas
transported by Sea Robin for Shipper pursuant to an executed
ITS Agreement.
2.2 Service hereunder shall be provided on an interruptible basis.
Interruption of service includes decreasing, suspending, or
discontinuing the receipt or delivery of gas in accordance with
the priorities set out in Section 8.3 of the General Terms and
Conditions. Service may be interrupted if Shipper fails to
comply with any provision of the General Terms and Conditions,
this Rate Schedule ITS or the ITS Agreement thereunder