Scg Pipeline Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2003, Docket: RP03-611-000, Status: Effective
Original Sheet No.137 Original Sheet No.137 : Superseded
GENERAL TERMS AND CONDITIONS
(continued)
(c) If no tests have been performed to determine the degree of inaccuracy,
or measurement equipment is out of service, the quantity of gas shall be
estimated:
(1) By using the registration of any existing and agreed upon check
equipment considered by parties concerned to be registering accurately, or in
the absence of such facilities,
(2) By correcting the error, if the quantity or percentage of error is
ascertainable by calibration, test, or mathematical calculation, or if neither
of the two foregoing procedures are applicable,
(3) By relating the quantity of receipt or delivery to receipts or
deliveries during periods under similar conditions when the measurement
equipment was deemed to have been registering accurately.
16.7 Preservation of Records. Each party shall preserve for a period of at
least two (2) years all test data, charts and other similar records or such
longer period as may be required by any duly constituted authority having
jurisdiction.
16.8 Flow Control. The Pipeline shall control flow of gas into and out
of its facilities at all measurement facilities, but may allow the following
if all of Pipeline's operating standards and requirements are met: (a)
Pipeline may allow third parties to control flow into the Pipeline's
facilities, but reserves the right to override the third party's flow control
equipment, and (b) Pipeline may allow third parties to control flow out of the
Pipeline's facilities, but reserves the right to override the third party's
flow control equipment.