GENERAL TERMS AND CONDITIONS
(continued)
16.3 Access to Equipment and Records. Each party shall have the right to be
present at the time of any installing, reading, cleaning, changing, repairing,
inspecting, testing, calibrating or adjusting done in connection with the
other's equipment used in measuring receipts and deliveries hereunder. The
records from such measurement equipment shall remain the property of their
owner, but upon request each will submit to the other its records and charts,
together with calculations therefrom, for inspection and verification, subject
to return within thirty (30) Days after receipt thereof.
16.4 Pressure Protection. Pressure regulation, pressure override and
pressure relief valve or other pressure limiting devices installed and
operated by Pipeline at the measuring station or at or near each
interconnection of Pipeline's facilities with facilities of third parties
shall only be for the purpose of operation and protection of Pipeline's
measurement equipment and Pipeline's facilities.
16.5 Test of Meters. The accuracy of the Pipeline's and Shipper's
measurement equipment shall be verified by Pipeline and Shipper at reasonable
intervals and, if requested, in the presence of representatives of the
Pipeline and Shipper.
(a) Pipeline and Shipper shall not be required to verify the accuracy of
orifice meter equipment more frequently than once in any thirty (30) Gas Day
period.
(b) Pipeline and Shipper shall not be required to verify the accuracy of
measurement equipment, other than orifice meter equipment, more frequently
than once in any ninety (90) Gas Day period.
(c) Pipeline and Shipper shall not be required to verify the accuracy of the
gas chromatograph or other heating value measurement device more frequently
than once in any thirty (30) Gas Day period.