Scg Pipeline Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2003, Docket: RP03-611-000, Status: Effective
Original Sheet No.62 Original Sheet No.62 : Superseded
GENERAL TERMS AND CONDITIONS
(continued)
under long-term contracts, cost of the facilities, operation and
maintenance, applicable taxes, administrative and general expenses
attributable to the facilities, the system net revenues Pipeline estimates
will be generated subsequent to such construction, depreciation, return on
investment and the availability of capital funds on terms and conditions
acceptable to Pipeline. In estimating the system net revenues to be
generated, Pipeline will evaluate the revenue generated from long-term firm
transportation contracts and other system benefits.
3.3 Any monetary reimbursement due Pipeline by Shipper pursuant to this
Section 3 shall be due and payable to Pipeline within ten (10) Days of receipt
by Shipper of Pipeline's invoices for same; provided, however, subject to
Pipeline's written consent such monetary reimbursement, plus carrying charges
thereon, may be amortized over a mutually agreeable period not to exceed the
primary contract term of the Service Agreement between Pipeline and Shipper.
3.4 Nothing in this statement of policy shall require Pipeline to file an
application to build or modify facilities or to render service. Further,
nothing in this policy statement shall prevent Pipeline from contesting an
application for service or a request to compel the rendition of service filed
at the Commission. Pipeline reserves the right to seek a waiver of the
policies set forth in this Section 3 for good cause shown during any
proceeding before any duly constituted regulatory authority.
3.5 Nothing in this Tariff shall require Pipeline to file an application for
a certificate of public convenience and necessity with the Commission.
Further, nothing in this Tariff prevents Pipeline from contesting an
application for service filed with the Commission.