Sabine Pipe Line Company LLC

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 07/31/1993, Docket: RS92- 78-003, Status: Effective

Original Sheet No. 443 Original Sheet No. 443 : Superseded

 

are the charges set forth in such IT-1 Rate Schedule

which apply to service rendered under this Service

Agreement:

 

(List applicable charges by reference to

Section 3 of IT-1 Rate Schedule)

 

3.2 Sabine shall have the right, from time to time, to file

and to seek FERC approval, pursuant to Section 4 of the

Natural Gas Act, to change any rates, charges or

provisions set forth in its IT-1 Rate Schedule or its

General Terms and Conditions, incorporated by reference

as part of this Service Agreement. Sabine shall place

such changes in effect in accordance with Section 4(c)

of the Natural Gas Act and this Service Agreement shall

be deemed to include such changes which become

effective by operation of law or by FERC Order, without

prejudice to Shipper's right to protest the same.

 

3.3 This Service Agreement in all respects is subject to

the provisions of Sabine's IT-1 Rate Schedule, or

superseding rate schedule(s), and applicable provisions

of the General Terms and Conditions included by

reference in such IT-1 Rate Schedule filed by Sabine

with the FERC, all of which are by reference made a

part hereof.

 

3.4 Any changes or additions to this Service Agreement are

set forth in Exhibit C.

 

 

ARTICLE IV

 

 

4. REGULATORY REQUIREMENTS AND CONDITIONS PRECEDENT

 

4.1 The transportation arrangements provided for in this

Service Agreement are subject to the provisions of Part

284 of the FERC's regulations, as amended from time to

time.

 

4.2 Transportation of gas provided for under the terms and

provisions of this Service Agreement shall not commence

until the following conditions have been met:

 

a) Any construction, acquisition, or expansion of

facilities necessary to commence transportation

has been completed;