Sabine Pipe Line Company LLC
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/31/1993, Docket: RS92- 78-003, Status: Effective
Original Sheet No. 283 Original Sheet No. 283 : Superseded
14.13 Alterations and Repairs
Sabine shall have the right to interrupt the
transportation of gas when necessary to test, alter,
modify, enlarge or repair any facility or property
comprising a part of, or appurtenant to, its System, or
otherwise related to the operation thereof. Sabine
shall endeavor to cause a minimum of inconvenience and,
except in the cases of emergency, shall give advance
notice of its intention to interrupt the transportation
of gas and of the expected magnitude of such
interruptions.
14.14 Quality Control and Electronic Communication
Equipment
Sabine shall have the right to collect from the
interconnecting Operator/Shipper the cost of any gas
analysis, quality control and/or electronic
communication equipment which Sabine, in its reasonable
discretion, determines is required at any Receipt
Point(s) or Delivery Point(s) to monitor the quality
and quantity of gas received or delivered by Sabine.
14.15 Installation of Flow Control Equipment
Sabine may construct, install, and operate flow control
equipment, telemetry equipment or electronic flow
computers, at any location on its system, whenever
Sabine determines in its reasonable judgment, that such
equipment will contribute to the safe, reliable,
efficient and orderly operational integrity of its
system.
14.16 Regulatory Precedence
Nothing in this Section 14 shall require Sabine to file
an application for a certificate of public convenience
and necessity under Section 7(c) of the Natural Gas
Act. Sabine reserves the right to seek a waiver of the
policy set forth herein, for good cause shown, during
any proceeding before the FERC