Sabine Pipe Line Company LLC
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/31/1993, Docket: RS92- 78-003, Status: Effective
Original Sheet No. 280 Original Sheet No. 280 : Superseded
of a meter test has been given and the party receiving
such notice is not present or represented at the time
set, the other party may proceed with the test and any
necessary adjustment.
14.5 Orifice Meters
Orifice meters shall be installed and gas quantities
measured, in accordance with the standards prescribed
in ANSI/API 2530.
14.6 Electronic Flow Computers or Telemetry Equipment
It is recognized that telemetry equipment, electronic
flow computers or other types of flow computers have
been developed that permit direct computation of gas
quantities without the use of charts. Where the
substitution of these devices is deemed acceptable by
mutual agreement between Sabine and the interconnecting
Operator, in exercise of their reasonable judgment, the
use of electronic flow computers for custody transfer
will be permitted.
14.7 New Measurement Techniques
If at any time a new method or technique is developed
with respect to gas measurement or the determination of
the factors used in such gas measurement, such new
method or technique may be substituted by mutual
agreement between Sabine and the interconnecting
Operator.
14.8 Correction of Metering Errors
If upon any test, the percentage of inaccuracy of any
measuring equipment is found to be in error by not more
than two percent (2%), the previous recordings of such
equipment shall be considered accurate in computing
receipts and deliveries, but such equipment shall be
adjusted at once to record accurately. If upon any
test, the percentage of inaccuracy of any measuring
equipment is found to be in error by more than two
percent (2%), the registration thereof shall be
corrected for a period extending back to the time such
inaccuracy occurred, or if such time is not