Sabine Pipe Line Company LLC
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/31/1993, Docket: RS92- 78-003, Status: Effective
Original Sheet No. 120 Original Sheet No. 120 : Superseded
IT-1 RATE SCHEDULE
INTERRUPTIBLE TRANSPORTATION SERVICE
1. AVAILABILITY
This Rate Schedule is available to any Shipper for
interruptible transportation of gas by Sabine Pipe Line
Company (Sabine) under the authority and provisions of
Part 284 of the FERC's Regulations, provided that:
a) Sabine determines that it has available capacity
to render the interruptible transportation service
and is able to provide said transportation;
b) Any construction, acquisition, or expansion of
facilities necessary to commence and provide the
interruptible transportation service has been
completed;
c) Any Shipper requesting interruptible
transportation service under Section 311 of the
Natural Gas Policy Act (NGPA) has provided written
certification including sufficient information to
verify that requested service qualifies under
Section 311 of the NGPA, and certifications have
been received from the qualifying local
distribution companies or intrastate pipelines in
accordance with Section 4 of the General Terms and
Conditions;
d) Shipper satisfies the credit worthiness criteria
in accordance with Section 9 of the General Terms
and Conditions; and
e) Shipper executes an Interruptible Service
Agreement in the form contained in this FERC Gas
Tariff for service under this Rate Schedule.
2. APPLICABILITY AND CHARACTER OF SERVICE
a) Transportation service hereunder, through all or
any portion of Sabine's System, shall be
interruptible, subject to the availability of