Portland Natural Gas Transmission System
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2010, Docket: RP10-885-000, Status: Effective
Original Sheet No. 582 Original Sheet No. 582
ARTICLE IV - RATE SCHEDULES AND GENERAL TERMS AND CONDITIONS
This Contract and all provisions contained or incorporated herein are
subject to the provisions of Rate Schedule FT and of the General Terms and
Conditions of Transporter's Tariff, as such may be revised or superseded from
time to time, all of which by this reference are made a part hereof. The
General Terms and Conditions and Rate Schedule FT shall control in the event
of a conflict between the General Terms and Conditions or Rate Schedule FT and
this Contract. All of the terms defined in Transporter's Tariff shall have
the same meaning wherever used in this Contract.
ARTICLE V - TERM
1. The Commencement Date shall be [state date].
2. This Contract shall be effective as of the date first hereinabove
written, provided, however, that Transporter shall have no liability under
this Contract and shall be under no obligation to receive or to deliver any
quantities of Gas hereunder, and Shipper shall be under no obligation to pay
for transportation, prior to the Commencement Date.
3. This Contract shall continue in force and effect until [state
expiration date]; provided, however, that if the FERC authorizes Transporter
to abandon service to Shipper on an earlier date, this Contract shall
terminate as of such earlier date.
4. The termination of this Contract by expiration of fixed Contract
term or by termination notice provided by Shipper triggers pregranted
abandonment under Section 7 of the Natural Gas Act as of the effective date of
the termination.
5. Any provision of this Contract necessary to correct imbalances or
to make payment under this Contract as required by the Tariff will survive the
other parts of this Contract until such time as such balancing or payment has
been accomplished.