Portland Natural Gas Transmission System

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/01/2006, Docket: RP06-449-000, Status: Effective

Original Sheet No. 342 Original Sheet No. 342 : Effective

 

GENERAL TERMS AND CONDITIONS (Continued)

 

10.3 Repair and Maintenance. Transporter shall have the right to

interrupt or curtail service in whole or in part on all or a portion of its

System from time to time to perform repair or maintenance that are non-routine

in nature, and other construction or testing procedures as necessary to

maintain operational capability on the System or to comply with applicable

regulatory requirements. Transporter shall exercise due diligence to schedule

such activity so as to minimize disruptions of service to Shippers, and shall

confirm Nominations as set forth in Section 7.5(b) herein taking into account

routine repair and maintenance.

 

(a) Annual Notices. No later than each March 31, Transporter

will post on its Interactive Internet Website a projection of repair,

maintenance, and other construction or testing procedures scheduled for the

upcoming Year, from April 1 through March 31, which are likely to affect

Transporter's capacity. Transporter may in good faith modify the projected

schedule in any manner, at any time during such Year, and will provide notice

of any change in the schedule as soon as possible after deciding to make such

a change. Transporter will have no liability if actual activity does not

conform to the projected annual schedule.

 

(b) Monthly Notices. At least ten (10) Days prior to the first

Day of each Month, Transporter will post on its Interactive Internet Website a

schedule of repair, maintenance, and other construction or testing procedures

for such Month which are likely to affect System Capacity. Such notice will

include an estimate of the duration of the activity. Transporter will have no

liability if it must modify the schedule or perform additional unscheduled

repair, maintenance and other construction or testing procedures during the

Month.

 

10.4 Make-up Service. In the event of interruption or curtailment of

service, Shipper shall be given the opportunity on a subsequent Day or Days to

make up such loss of service provided that such make-up service shall not

preclude or interfere with the service priorities set forth in Section 7. In

no event shall Shipper be liable for duplicative charges with respect to

interrupted scheduled service, for which Shipper has previously paid, which

was interrupted and subsequently made up pursuant hereto.