Portland Natural Gas Transmission System
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2010, Docket: RP10-885-000, Status: Effective
First Revised Sheet No. 340 First Revised Sheet No. 340
Superseding: Original Sheet No. 340
GENERAL TERMS AND CONDITIONS (Continued)
9. RECEIPT POINTS AND DELIVERY POINTS
9.1 Receipt Points. The Primary Receipt Point(s) at which Transporter
will receive Gas from Shipper or for Shipper's account shall be those set
forth on Schedule 1 appended to the Gas Transportation Contract. Such
Schedule 1 shall also set forth the Maximum Daily Quantity applicable to each
Primary Receipt Point. Maximum Contract Demand is listed in Schedule 1 of Gas
Transportation Contracts for firm and winter firm service. Subject to the
availability of capacity, all other Receipt Points shall be available, under
18 C.F.R. Part 284 of the FERC's Regulations, as Secondary Receipt Point(s)
for Shippers with Gas Transportation Contracts for firm service, subject to
Section 8.1(b)(1) herein.
9.2 Additions and Deletions of Primary Receipt Points. Subject to
Section 9.5 herein, the currently effective Schedule 1 appended to each Gas
Transportation Contract may be revised from time to time in order to reflect
additions or deletions of Primary Receipt Points, or changes in the Maximum
Contract Demand or Maximum Daily Quantities applicable to Primary Receipt
Points.
9.3 Delivery Points. The Primary Delivery Point(s) at which
Transporter will make Gas available to or on behalf of Shipper shall be those
set forth on Schedule 2 appended to the Gas Transportation Contract(s). Such
Schedule 2 shall also set forth the Maximum Daily Quantity applicable to each
such Primary Delivery Point. Transporter shall make deliveries at each
Delivery Point as nearly as practicable at System line pressures. Subject to
the availability of capacity, all other Delivery Points shall be available,
under Part 284 of the FERC's Regulations, as Secondary Delivery Point(s) for
Shippers receiving firm service, subject to Section 8.1(b)(1) herein.
9.4 Additions and Deletions of Primary Delivery Points. Subject to
Section 9.5 herein, the currently effective Schedule 2 appended to each Gas
Transportation Contract may be revised from time to time in order to reflect
additions or deletions of Primary Delivery Points or changes in the Maximum
Daily Quantities applicable to such Primary Delivery Points.
9.5 Primary Receipt and Delivery Points to be Added Only where
Capacity Available. Shippers may add a Primary Delivery Point or Primary
Receipt Point for firm service only if sufficient firm capacity is available
at that point of Segment and there are no pending requests for firm service at
that point or Segment.