GENERAL TERMS AND CONDITIONS (Continued)
confirmations by Transporter from upstream and downstream connected parties;
9:00 p.m. for Transporter to provide Scheduled Quantities to affected Shippers
and point operators (all listed time are Central Clock Time on the Day of gas
flow). Scheduled Quantities resulting from Intraday-2 Nominations should be
effective at 9:00 p.m. Central Clock Time on the Day of gas flow. Bumping is
not allowed during the Intraday-2 Nomination Cycle.
7.3 Measurement Variance.
Shipper shall receive or cause the applicable Measurement Variance
Quantity to be furnished in kind each Month. If necessary, Transporter shall
use the applicable Measurement Variance Factor to adjust a Shipper's
Scheduled Quantities, or to calculate the Measurement Variance Quantity that a
Shipper may tender at the applicable Receipt Point in lieu of an adjustment to
the Scheduled Quantity. In no instance shall the Measurement Variance
Quantity be less the one (1) DTH.
7.4 Allocation of Capacity.
(a) On each Day Transporter shall determine with respect to all
Gas Transportation Contracts:
(1) the total quantities which all Shippers have nominated
to be received on that Day;
(2) the total quantities which all Shippers have nominated
to be delivered on that Day; and
(3) Transporter's capacity available in each pipeline
Segment to perform all of the nominated services.
(b) If due to any cause whatsoever Transporter is unable, on any
Day, to satisfy all Nominations for service through any pipeline Segment
pursuant to the procedures in Section 7.1 above, then Transporter shall
allocate available service in the constrained Segment according to the
following allocation procedure: