RATE SCHEDULE FT-FLEX (Continued)
v) Authorized overrun charge. For each Month, the maximum authorized
overrun charge payable by Shipper shall be equal to the applicable maximum rate
for service under Rate Schedule IT, multiplied by the sum of the Authorized
Overrun Scheduled Quantity or Quantities during such Month for such Shipper.
vi) Other Charges. These include any other charges as may be
applicable from time to time pursuant to the General Terms and Conditions or as
otherwise authorized by the FERC.
vii) Capacity Release Credits. To the extent Shipper releases capacity
in any Month pursuant to Section 11 of the General Terms and Conditions, Shipper