Pine Prairie Energy Center, LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/01/2007, Docket: RP07-563-000, Status: Effective

Original Sheet No. 123 Original Sheet No. 123 : Effective

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

4.12 Marketing Fee. If PPEC and the Releasing Customer

so agree, PPEC may receive a negotiated fee for its marketing

efforts.

 

4.13 Limitations.

 

(a) Releases and assignments hereunder shall be for

period(s) of one or more Day(s) and the maximum term shall not

extend beyond the expiration of this FERC Gas Tariff provision or

beyond the expiration of the Releasing Customer's Storage Service

Agreement.

 

 

(b) PPEC may invalidate any offer to release or any bid

subsequent to its posting on the Internet Web Site which does not

conform to the requirements of this Section and the other

provisions of this FERC Gas Tariff and such invalidated offer or

bid shall be deemed null and void.

 

(c) Any terms and conditions imposed on the offer to

release by the Releasing Customer as provided for in this Section

4 must be objectively stated, reasonable, capable of

administration or implementation by PPEC without any material

increase in burden or expense, applicable to all potential

bidders, not unduly discriminatory, and consistent with the terms

and conditions of this FERC Gas Tariff and Releasing Customer's

Storage Service Agreement.

 

(d) A Releasing Customer may re-release to the same

Replacement Customer, where such first release was not subject to

posting and bidding pursuant to Section 4.4, for a term of 31 Days

or less, only if: 1) a period of 28 Days has elapsed after the

first release for 31 Days or less has expired or 2) the Point(s)

of Receipt and/or Point(s) of Delivery for the re-release is (are)

different from the Point(s) of Receipt and/or Point(s) of Delivery

of the first release or 3) the Releasing Customer causes the

posting of an offer to release capacity or of a pre-arranged

transaction to be made, and capacity is allocated on the basis of

bids submitted.

 

(e) Recall Provisions. If the Releasing Customer

retains recall rights, Releasing Customer's offer to release

capacity shall clearly specify the conditions precedent to such

recall and whether the recall right retained by Releasing Customer

is on a full Day or partial Day basis. The Releasing Customer

shall provide capacity recall notification to PPEC via the

Internet Web Site. The recall notification shall specify the

recall notification period for the specified effective Day, as

well as any other information needed to uniquely identify the

capacity being recalled. PPEC shall support the following recall

notification periods for all released capacity subject to recall

rights:

 

(1) Timely Recall Notification:

 

(A) A Releasing Customer recalling capacity should provide

notice of such recall to PPEC and the first Replacement

Customer no later than 8:00 A.M. CCT on the Day that

Timely Nominations are due;