IW RATE SCHEDULE

INTERRUPTIBLE WHEELING SERVICE

(Continued)

 

3. RATES AND CHARGES

 

 

Customer shall pay the rates and charges for Interruptible

wheeling service under this Rate Schedule including the applicable

wheeling rate components set forth in the IW Rate Statement and as

described below:

 

(a) Interruptible Wheeling Charge. A charge for each

Dth of Customer's Gas wheeled by PPEC.

 

 

(b) Fuel Reimbursement. The amount of Gas for fuel and

losses determined in accordance with Section 19 of this FERC Gas

Tariff and as set forth in Customer's Hub Services Agreement per

each Dth of Gas received from Customer for wheeling.

 

 

(c) Regulatory Fees and Charges. Customer shall

reimburse PPEC for all fees and charges, as required by the

Commission or any other regulatory body, that are related to

service provided under this Rate Schedule, as set forth in the Hub

Services Agreement.

 

 

(d) Taxes. Customer shall reimburse PPEC for all

applicable taxes as may be assessed, as set forth in Section 15 of

the General Terms and Conditions of this FERC Gas Tariff and in

Customer's Hub Services Agreement.

 

4. INVOICE

 

 

Each invoice for Interruptible wheeling service shall reflect

the applicable charges set forth under Section 3 of this Rate

Schedule at rates and terms set forth in Customer's Hub Services

Agreement.

 

5. TERM

 

The term for service under this Rate Schedule shall be as set

forth in Customer's Hub Services Agreement.

 

6. AUTHORIZATION, RATES, TERMS AND CHANGES

 

 

6.1 The Hub Services Agreement and the respective

obligations of the parties hereunder are subject to all valid

laws, orders, rules and regulations of duly constituted

authorities having jurisdiction, and are conditioned upon the

issuance, by FERC, and any state or local governmental agency

having jurisdiction, of requisite authorization for PPEC to

provide the wheeling service contemplated hereby and to construct

and operate the Gas wheeling facilities necessary to provide such

wheeling service and for any connected pipeline to transport Gas

to/from the Point(s) of Receipt/Delivery necessary to effect the