Pine Prairie Energy Center, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2007, Docket: RP07-563-000, Status: Effective
Original Sheet No. 43 Original Sheet No. 43 : Effective
IW RATE SCHEDULE
INTERRUPTIBLE WHEELING SERVICE
1. AVAILABILITY
This Rate Schedule is available to any Customer for the
purchase of Interruptible Gas wheeling service from PPEC, provided
that:
(a) PPEC has determined that it has sufficient
operationally available Interruptible wheeling, receipt and
delivery capacity to perform service Customer has requested;
(b) PPEC has determined that service Customer has
requested will not interfere with efficient operation of its
system or with Firm Storage Services;
(c) Customer and PPEC have executed a Hub Services
Agreement under this Rate Schedule;
(d) Customer accepts responsibility for arranging any
upstream and/or downstream transportation service required for
utilization of the wheeling service provided under this Rate
Schedule; and
(e) Service under this Rate Schedule may not be
available to the extent that PPEC would be required to construct,
modify, expand or acquire any facilities to enable PPEC to perform
the requested services.
2. APPLICABILITY AND CHARACTER OF SERVICE
This Rate Schedule shall apply to all Interruptible wheeling
service rendered by PPEC to Customer through use of PPEC's storage
facility located in Louisiana pursuant to an executed Hub Services
Agreement.
Interruptible wheeling service rendered by PPEC to Customer
under this Rate Schedule shall consist of the transportation of
Gas, on an Interruptible basis, by PPEC for Customer on PPEC's
system between agreed upon Point(s) of Receipt and Point(s) of
Delivery.
PPEC shall, on an Interruptible basis, receive for Customer
at Point(s) of Receipt and shall transport and deliver at the
Point(s) of Delivery, less Fuel Reimbursement, daily quantities of
Gas up to the Maximum Daily Wheeling Quantity ("MDTQ") as
specified in Customer's Hub Services Agreement; provided, however,
PPEC shall not be obligated to receive, transport and/or deliver
quantities of Gas on any Day in excess of the quantity nominated
and scheduled for that Day. Interruptible wheeling service shall
be available only in the event that all Firm Storage Service needs
have been satisfied. Interruptible wheeling service shall also
include title transfers pursuant to Section 20.2 of the General
Terms and Conditions of this FERC Gas Tariff.