Pine Prairie Energy Center, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2007, Docket: RP07-563-000, Status: Effective
Original Sheet No. 30 Original Sheet No. 30 : Effective
FL RATE SCHEDULE
FIRM LOAN SERVICE
(Continued)
(c) The receipt on any Day during the Injection Period
stated in Customer's executed Firm Loan Service Agreement and
injection into storage of Customer's Gas per Customer's nomination
up to the Maximum Daily Injection Quantity ("MDIQ") stated in
Customer's executed Firm Loan Service Agreement, provided that
Customer delivers the nominated quantity plus Fuel Reimbursement
to the Point(s) of Receipt, and Customer's total injections may
not exceeded Customer's Maximum Loan Quantity; and
(d) The tender by Customer of sufficient quantities of
Gas under Section 2.1(c) to ensure that Customer's Loan Balance
equals zero (0) at the end of the Injection Period. Customer
shall not have the right to inject or withdraw Gas during the
period of time between the Withdrawal Period and the Injection
Period.
2.2 If Customer fails to replace or replenish Gas advanced
by PPEC to Customer under this Rate Schedule at the agreed upon
time, PPEC may purchase replacement Gas and Customer shall pay
PPEC the cost of the replacement Gas, which shall include the
actual cost of replacement supplies and any costs or penalties
incurred by PPEC or its Customers as a result of Customer's
failure to deliver replacement Gas, plus all other costs incurred
by PPEC to secure such replacement Gas, including, but not limited
to, third-party marketing fees, transportation by third-party
pipeline companies, and all other costs for securing replacement
Gas.
3. RATES AND CHARGES
Customer shall pay rates and charges for firm loan service
under this Rate Schedule including the applicable loan rate
components set forth in the FL Rate Statement and as described
below:
(a) Firm Loan Reservation Charge. A monthly charge for
each Dth of Customer's Maximum Loan Quantity.
(b) Firm Loan Injection Charge. A charge for each Dth
of Gas injected into PPEC's facilities pursuant to Section 2.1(c)
of this Rate Schedule.
(c) Firm Loan Withdrawal Charge. A charge for each Dth
of Gas withdrawn from PPEC's facilities pursuant to Section 2.1(a)
of this Rate Schedule.
(d) Fuel Reimbursement. The amount of Gas for fuel and
losses determined in accordance with Section 19 of the General
Terms and Conditions of this FERC Gas Tariff and set forth in
Customer's Firm Loan Service Agreement.