FP RATE SCHEDULE
FIRM PARKING SERVICE
(Continued)
(c) The storage of Gas in amounts up to Customer's
Maximum Park Quantity; and
(d) The withdrawal from storage on any Day during the
Withdrawal Period stated in Customer's executed Firm Parking
Service Agreement and delivery of Customer's Gas per Customer's
nomination to the Point(s) of Delivery up to the Maximum Daily
Withdrawal Quantity ("MDWQ") as stated in Customer's executed Firm
Parking Service Agreement, provided that Customer has a quantity
of Gas in Customer's Park Balance not less than the quantity
Customer shall have nominated for withdrawal on such Day.
Customer shall not have the right to inject or withdraw Gas during
the period of time between the Injection Period and the Withdrawal
Period.
3. RATES AND CHARGES
Customer shall pay rates and charges for firm parking service
under this Rate Schedule including the applicable parking rate
components set forth in the FP Rate Statement and as described
below:
(a) Firm Parking Reservation Charge. A monthly charge
for each Dth of Customer's Maximum Park Quantity.
(b) Firm Parking Injection Charge. A charge for each
Dth of Customer's Gas injected into PPEC's facilities pursuant to
Section 2.1(a) of this Rate Schedule during a given Month.
(c) Firm Parking Withdrawal Charge. A charge for each
Dth of Customer's Gas withdrawn from PPEC's facilities pursuant to
Section 2.1(d) of this Rate Schedule during a given Month.
(d) Fuel Reimbursement. The amount of Gas for fuel and
losses determined in accordance with Section 19 of the General
Terms and Conditions of this FERC Gas Tariff and set forth in
Customer's Firm Parking Service Agreement.
(e) Regulatory Fees and Charges. Customer shall
reimburse PPEC for all fees and charges, as required by the
Commission or any other regulatory body, that are related to
service provided under this Rate Schedule, as set forth in
Customer's Firm Parking Service Agreement.
(f) Taxes. Customer shall reimburse PPEC for all
applicable taxes as may be assessed PPEC, as set forth in Section
15 of the General Terms and Conditions of this FERC Gas Tariff and
in Customer's Firm Parking Service Agreement.