PetroLogistics Natural Gas Storage LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/03/2009, Docket: RP09-577-000, Status: Effective
Original Sheet No. 116 Original Sheet No. 116
affected Shippers and point operators, and to provide scheduled quantities to bumped Parties (notice
to bumped parties), (central clock time on the day prior to flow). Scheduled quantities resulting
from Intraday 1 Nominations should be effective at 5:00 p.m. on gas Day.
(4) Intraday 2 Nomination Cycle: 5:00 p.m. for nominations leaving control of the nominating
party; 5:15 p.m. for receipt of nominations by PetroLogistics (including from TTTSPs); 5:30 p.m. to
send Quick Response; 8:00 p.m. for receipt of completed confirmations by transporter from upstream
and downstream connected parties; 9:00 p.m. for PetroLogistics to provide scheduled quantities to
affected Shippers and point operators (notice to bumped) (central clock time on the day prior to flow).
Scheduled quantities resulting from Intraday 2 Nominations should be effective at 9:00 p.m. on gas
Day. Bumping is not allowed during Intraday 2 Nomination Cycle.
(f) For intra-day nominations, PetroLogistics will conform to the provisions established by
Shipper's Transporter, including hourly nomination deadlines.
(1) Except as stated above in 6.3(e), intra-day nominations for Firm Storage Service will be given
priority over scheduled and flowing Interruptible Storage Service.
(2) Intra-day nominations do not replace the remainder of a standing nomination. There is no
need to re-nominate if the intra-day nomination modifies an existing nomination.
(g) Upon confirmation from Shipper's Transporter, PetroLogistics will commence injection or
withdrawal for Shipper's account.
(h) Nominations received after the nomination deadline will be scheduled after the nominations
received before the nomination deadline.
(i) Shipper shall be responsible for all penalties and charges assessed by an upstream or
downstream Transporter which arise from Shipper's failure to provide delivery of the gas
quantities provided.
(j) A Replacement Shipper may submit a nomination at the earliest nomination opportunity after
PetroLogistics has been notified of the capacity release.
(k) Routine Maintenance. PetroLogistics shall have the right to interrupt or discontinue service
in whole or in part, from time to time to perform routine repair and maintenance on PetroLogistics'
system as necessary to maintain the operational capability of PetroLogistics' Facility or to comply
with applicable regulatory requirements. PetroLogistics shall exercise due diligence to schedule
routine repair and maintenance so as to minimize disruptions of service to Shippers and shall
provide reasonable notice of the same to Shippers.
6.4 Shipper shall make available and tender any gas to be injected or wheeled hereunder and
receive and accept delivery, upon tender by PetroLogistics, any gas requested to be withdrawn from
storage or wheeled. The quantity of gas stored for the account of Shipper shall be increased or
decreased upon injection or withdrawal of gas from storage, as applicable. Shipper shall not
(unless otherwise agreed by PetroLogistics) receive or deliver gas, nor shall PetroLogistics be
obligated to receive gas or deliver gas on an hourly basis at rates of flow in excess of 1/24 of
Shipper's MDRQ or MDDQ, respectively. As determined by PetroLogistics in it sole and reasonable