Panther Interstate Pipeline Energy, L.L.C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 02/01/2004, Docket: CP03-338-001, Status: Effective

Original Sheet No. 22 Original Sheet No. 22 : Effective

 

the requesting party if the measuring equipment tested is

found to be in error not more than two percent (2%).

 

(b) If, upon testing, any measuring equipment is found to be in

error by not more than two percent (2%), previous recordings

of such equipment shall be considered accurate in computing

deliveries of gas, but such equipment shall be adjusted at

once to record accurately.

 

(c) If, upon test, any measuring equipment shall be found to be

inaccurate by an amount exceeding two percent (2%), at a

recording corresponding to the average hourly rate of flow

for the period since the last preceding test, then any

previous recordings of such equipment shall be corrected to

zero error for any period that is known definitely, but in

case the period is not known or agreed upon, such correction

shall be for a period extending over one-half of the time

elapsed since the date of the last test, not exceeding a

correction period of sixteen days.

 

5. QUALIFICATION FOR SERVICE

 

5.1 Request for Service: All Shippers requesting firm transportation

service or interruptible transportation service must provide the

applicable information required by this Section 5 in order to

qualify for service. Requests must be provided by a means

consistent with Section 16 of these General Terms and Conditions.

Any material modification, in whole or in part, of an existing

transportation service shall be requested by Shipper's submission

of a new request for service with a notation that the service

requested is a modification of an existing service. No request

for service will be processed until a completed request on a form

provided by Transporter has been submitted by Shipper to

Transporter consistent with this Section 5. Transporter shall not

be obligated to accept a request which has been submitted more

than ninety (90) days prior to the proposed effective date, but

may do so on a non-discriminatory basis or where additional

facilities are required.

 

5.2 Required Information: Any request shall include the information

listed below. Shipper shall provide any additional information

reasonably required by Transporter to process the request;

provided that the request for additional information shall not

affect the priority of Shipper's request.