Original Sheet No. 11 Original Sheet No. 11 : Effective
be received; (2) Shipper has failed to make and properly
implement all necessary upstream arrangements on upstream
entities; or (3) Shipper has failed to nominate such quantities
consistent with Section 9 of the General Terms and Conditions of
this Tariff.
4.2 Delivery Points: All delivery points on Transporter's system
shall be available as delivery points for gas transported under
this Rate Schedule. Transporter shall not be required under any
circumstances to deliver gas at any delivery point where: (1)
the total quantity of gas scheduled for delivery on any Day is
less than that required for the accurate measurement of quantities
to be delivered; (2) Shipper has failed to make and properly
implement all necessary downstream arrangements on downstream
entities; or (3) Shipper has failed to nominate such quantities
consistent with Section 9 in the General Terms and Conditions of
this Tariff.
5. RATES AND CHARGES
5.1 Transportation Rates: Except to the extent Transporter and
Shipper have agreed in writing to a discounted rate, the
transportation rate is the maximum IT rate shown on the effective
Tariff Sheet No. 4. The Monthly Bill for service shall equal:
(a) The applicable IT Rate multiplied by the dekatherms of
natural gas transported and delivered by Transporter for
Shipper in the month pursuant to this Rate Schedule; and
(b) If applicable, any other charges pursuant to Section 5 of
this Rate Schedule.
5.2 New Facilities:
(a) In addition to the charges pursuant to Section 5.1 of this
Rate Schedule, if Transporter agrees to construct facilities
for service requested by Shipper, Transporter shall charge
Shipper an advance equal in amount to 100% of the estimated
costs (including a gross-up for the income tax effects or
reimbursement) of facilities constructed at the Shipper's
request in order to provide transportation service under
this Rate Schedule. Further, Transporter shall charge
Shipper an advance equal in amount to 100% of the estimated
costs (including a gross-up for the income tax effects of