(d) Determination of the Dakota Gasification Transition
Cost Surcharge
The Dakota Gasification Transition Cost Surchage shall
be determined on the basis of (1) the design units
underlying Panhandle's currently effective
Deliverability Charge for firm service and the Monthly
Inventory Charge for interruptible service for the
Market Area component of Rate Schedules WS, PS and FS
and the Market Area component of Rate Schedule IWS,
respectively, and (2) the Dakota Gasification
Transition Costs for the three (3) Months preceding
the effective date of the Surcharge on an "as-billed"
basis to reflect the basis of the billings submitted
to Panhandle by ANR. In addition, commencing with the
Surcharge to be effective on June 1, 1995, each Dakota
Gasification Transition Cost Surcharge shall be
adjusted as necessary to recover or to return the
balance in Panhandle's Unrecovered Dakota Gasification
Transition Cost Account as of two (2) Months prior to
June 1 over twelve (12) billing periods beginning each
June 1.
(e) Unrecovered Dakota Gasification Transition Cost
Account
Panhandle shall maintain an Unrecovered Dakota
Gasification Transition Cost Account to record the
cummulative monthly difference between actual Dakota
Gasification Transition Costs incurred and the actual
amounts recovered by Panhandle for Dakota Gasification
Transition Costs.
(f) Crediting of Refunds Received, Debiting of Additional
Surcharges
Commencing with the effective date of this Section
18.6, Panhandle shall credit all refunds received
which are related to its Dakota Gasification
Transition Costs to its Unrecovered Dakota
Gasification Transition Cost Account. Commencing with
the effective date of this Section 18.6, Panhandle
shall debit any similarly attributable additional
surcharge for its Dakota Gasification Transition Costs
to its Unrecovered Dakota Gasification Transition Cost