Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/30/2004, Docket: RP04-321-000, Status: Effective
Original Sheet No. 311 Original Sheet No. 311 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
(2) The GSR Reservation Surcharge during the Initial
GSR Cost Collection Period shall be designed to
recover the applicable GSR Costs over the three
(3) year Initial GSR Cost Collection Period using
the applicable firm service design determinants
underlying Panhandle's then effective rates for
service under Rate Schedules FT, EFT, SCT, LFT
and HFT.
The GSR Reservation Surcharge shall be based on
one-third (1/3) of the applicable GSR Costs to be
recovered pursuant to this Section 18.3. Such
GSR Costs shall include carrying charges for the
Initial GSR Cost Collection Period.
The GSR Reservation Surcharge shall be adjusted
annually during the Initial GSR Cost Collection
Period to reflect changes in the effective
billing determinants under Rate Schedules FT,
EFT, SCT, LFT and HFT. Such revisions to the
GSR Reservation Surcharge will become effective
twelve (12) months after the effective date of
the rate filing to establish the Initial GSR Cost
Collection Period or subsequent adjustment to the
GSR Reservation Surcharge. At least thirty (30)
Days prior to the effective date of the annual
adjustment to the GSR Reservation Surcharge,
Panhandle shall file with the Federal Energy
Regulatory Commission and post, as defined in
Section 154.2(d) of the Commission's Regulations,
Tariff Sheet Nos. 4, 5, 6, 15 and 17, together
with supporting computations.
(3) Rates for interruptible service under Rate
Schedules IT and EIT shall be adjusted to permit
the recovery of the applicable GSR Costs during
the three (3) year Initial GSR Cost Collection
Period using the applicable interruptible service
design determinants underlying Panhandle's