Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/17/2009, Docket: RP09-517-000, Status: Effective
Second Revised Sheet No. 291 Second Revised Sheet No. 291
Superseding: First Revised Sheet No. 291
GENERAL TERMS AND CONDITIONS
(Continued)
(ii) A capacity release for more than one year at the
maximum tariff rate.
(iii) A capacity release to an asset manager as
defined in Section 284.8(h)(3) of the
Commission’s Regulations.
(iv) A capacity release to a marketer participating
in a state-regulated retail access program as
defined in Section 284.8(h)(4) of the
Commission’s Regulations.
Such releases for which no bids are required may be
submitted electronically and shall be posted on the
Messenger® system upon confirmation by the
Replacement Shipper. The Capacity Release Service
Agreement Addendum number shall be provided when such
release is posted.
For non-biddable releases:
Timely Cycle
- posting of prearranged deals not subject to bid
are due by 10:30 a.m.;
- contract issued within one hour of award posting
(with a new contract number, when applicable);
nomination possible beginning at the next
available nomination cycle for the effective date
of the contract. (Central Clock Time)
Evening Cycle
- posting of prearranged deals not subject to bid
are due by 5:00 p.m.;
- contract issued within one hour of award posting
(with a new contract number, when applicable);
nomination possible beginning at the next
available nomination cycle for the effective date
of the contract. (Central Clock Time)
Intraday 1 Cycle
- posting of prearranged deals not subject to bid
are due by 9:00 a.m.;
- contract issued within one hour of award posting
(with a new contract number, when applicable);
nomination possible beginning at the next
available nomination cycle for the effective date
of the contract. (Central Clock Time)