Original Sheet No. 285 Original Sheet No. 285 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
(5) The new interconnect must not result in any minimum
pressure receipt or delivery requirement by Panhandle,
unless Panhandle agrees otherwise, such agreement shall
not be unreasonably withheld, and Panhandle shall not be
responsible for any downstream parties' facilities, the
operation or maintenance of such facilities, or the
delivery of any unauthorized volumes to the facilities;
(6) The service supporting the interconnect as well as the
construction of the new facilities must conform with the
provisions of Panhandle's FERC Gas Tariff, Third Revised
Volume No. 1 as well as applicable regulatory
requirements;
(7) The proposed interconnect must not cause Panhandle to be
in violation of any applicable environmental or safety
laws or regulations with respect to the facilities
required to establish an interconnect with Panhandle's
existing facilities; and
(8) The proposed interconnect must not cause Panhandle to be
in violation of its right-of-way agreements or any other
contractual obligations with respect to the interconnect
facilities.
Panhandle will respond to each request for interconnect facilities
within sixty (60) days after receiving a written request containing
reasonably sufficient and reliable information necessary for
Panhandle to make a determination pursuant to this Section 13.