13. POLICY FOR CONSTRUCTION OF NEW RECEIPT OR DELIVERY FACILITIES
All requests for new interconnects must be made in writing. The
party requesting the new interconnect shall reimburse Panhandle or
cause Panhandle to be reimbursed for any and all reasonable costs and
expenses incurred in constructing, establishing or modifying the
facilities required to establish a new interconnection on existing
facilities for receipt or delivery of Gas hereunder. Such
reimbursement shall be received by Panhandle prior to commencement of
service, unless otherwise agreed. In the alternative, the party
requesting the interconnect may perform the construction at its own
cost in compliance with Panhandle's technical requirements. In this
regard, all new receipt and delivery meters shall require EGM which
shall be owned by Panhandle and all new delivery meters shall require a
Flow Control Device with pressure override features that can be
remotely operated by Panhandle. Panhandle also must be the custody
transfer party at the proposed facility.
In addition to the above requirements, Panhandle will agree to
construct a new interconnect or modify an existing interconnect on
the following terms:
(1) The construction of the new interconnect will not create
any significant operational problems for Panhandle;
(2) The proposed interconnect will not adversely affect the
rendition of existing service or adversely alter the
operation of the pipeline system;
(3) The new interconnect must be at a mutually agreeable
location on the Panhandle system; provided, however, that
Panhandle may not deny a customer's request for specific
placement of the interconnect without adequate
operational, environmental, or legal justification;
(4) In order to properly and prudently design and size the new
interconnect, Panhandle must be provided with reasonable
and reliable data concerning the interconnecting
facilities, including delivery pressures, and anticipated
hourly, daily, monthly and annual volume levels of the
service that supports the new interconnect and such other
data as is reasonably required to construct the
interconnect facility;