Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/30/2004, Docket: RP04-321-000, Status: Effective
Original Sheet No. 270 Original Sheet No. 270 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
(i) Farm Tap
A Point of Delivery on Panhandle's pipeline system
which is required under the terms of a right-of-way
agreement between the landowner and Panhandle and at
which Gas is delivered under Rate Schedules SCT or
EFT for domestic and/or agricultural use shall be
defined as a Farm Tap. A Shipper's deliveries at a
Farm Tap shall not be subject to the terms set out in
(g) and (h) above but shall be subject to the terms
of (a) and (c) above. Excess receipts and excess
deliveries shall be determined on a basis consistent
with the measurement frequency for the Farm Tap
delivery meters.
(j) Irrigation Tap
A Point of Delivery on Panhandle's pipeline system
which is required under the terms of a right-of-way
agreement between the landowner and Panhandle and at
which Gas is delivered under Rate Schedules EFT or
EIT for purposes of irrigation shall be defined as an
Irrigation Tap. A Shipper's deliveries at an
Irrigation Tap shall not be subject to the terms set
out in (g) and (h) above but shall be subject to the
terms of (a), (b) and (c) above. Excess receipts and
excess deliveries shall be determined on a quarterly,
rather than on a Monthly basis.