Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/17/2009, Docket: RP09-517-000, Status: Effective
First Revised Sheet No. 247 First Revised Sheet No. 247
Superseding: Original Sheet No. 247
GENERAL TERMS AND CONDITIONS
(Continued)
(i) the sum of the Quantities of Gas nominated by the
Replacement Shipper from any secondary firm
Point(s) of Receipt, together with the sum of the
Quantities of Gas nominated from primary firm
Point(s) of Receipt, adjusted for Fuel
Reimbursement, shall not exceed the Maximum Daily
Contract Quantity in the Replacement Shipper's
Service Agreement; provided, however, if the
Replacement Shipper utilizes two (2) or more
discrete pipeline segments, the sum of the
Quantities of Gas nominated by the Replacement
Shipper from all Point(s) of Receipt may exceed
the Maximum Daily Contract Quantity specified in
the Service Agreement so long as the Quantities
nominated for transportation in a pipeline segment
do not exceed the Maximum Daily Contract Quantity
applicable to such segment; and
(ii) the sum of the Quantities of Gas nominated by
the Releasing Shipper from any secondary firm
Point(s) of Receipt, together with the sum of
the Quantities of Gas nominated from primary firm
Point(s) of Receipt, adjusted for Fuel
Reimbursement, shall not exceed the Maximum Daily
Contract Quantity not relrased in the Releasing
Shipper's Service Agreement; provided, however,
that where a Releasing Shipper releases a segment
or segments of its service rights, the Releasing
Shipper may nominate for Transportation on any
Day, up to the Maximum Daily Contract Quantity
not released in its Service Agreement applicable
to any segment wherein it has retained service
rights.
(iii) A Releasing Shipper and/or a Replacement Shipper
may segment its Primary Path to forwardhaul and
backhaul Quantities of Gas to the same Point of
Receipt. In such a segmented transaction, the
Shipper may exceed its Maximum Daily Contract
Quantity at that Point of Receipt and the Shipper
may nominate Quantities of Gas in each segment up
to the Shipper's Maximum Daily Contract Quantity
for such segment; provided, however, the
Quantities nominated to flow in the opposite
direction of the flow in the Primary Path shall be
considered to be outside the Shipper's Primary
Path for scheduling purposes.
(iv) If the Releasing Shipper and the Replacement
Shipper nominate Quantities of Gas in segments that
overlap, the Quantities shall be scheduled in
accordance with Section 8.8 of these General Terms