Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/17/2009, Docket: RP09-517-000, Status: Effective
First Revised Sheet No. 246 First Revised Sheet No. 246
Superseding: Original Sheet No. 246
GENERAL TERMS AND CONDITIONS
(Continued)
in each segment up to the Shipper's Maximum Daily
Contract Quantity assigned to such segment; provided,
however, the Quantities nominated to flow in the
opposite direction of the flow in the Primary Path
shall be considered to be outside the Shipper's
Primary Path for scheduling purposes.
(b) If the Shipper's Service Agreement has been released in
part to a Replacement Shipper pursuant to Section 15 of
these General Terms and Conditions: