Panhandle Eastern Pipe Line Company, LP
THIRD REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2009, Docket: RP10-10-000, Status: Effective
Eighth Revised Sheet No. 9 Eighth Revised Sheet No. 9
Superseding: Seventh Revised Sheet No. 9
CURRENTLY EFFECTIVE RATES
RATE SCHEDULE IOS
IN/OUT STORAGE
Each rate set forth on this tariff sheet is the currently effective rate pertaining to the
particular rate schedule to which it is referenced, but each such rate is separate and independent
and the change in any such rate shall not thereby effect a change in any other rate schedule.
Maximum Minimum
Rate Rate Fuel
Description Per Dt. Per Dt. Reimbursement
Deliverability Charge $ 3.35 1/ - -
Capacity Charge 40.28¢ 1/ - -
Injection Charge 0.33 0.33¢ 1.59%
Withdrawal Charge 0.33 0.33 0.72
Overrun Charge 14.85 - -
1/ Maximum rate applicable for capacity release with a term of more than one year.