5. OVERRUN AND UNDERRUN, BALANCING AND PENALTY PAYMENTS (Continued)
5.2 Restricted Entitlement Events:
(a) Restricted Delivery--Paiute System
(1) Applicability: This section applies to both firm and
interruptible transportation service under Rate
Schedules FT-1 and IT-1 when Paiute initiates general
system entitlement restrictions to alleviate operating
conditions or events which threaten or could threaten
the safe operation or integrity of Paiute's system.
Conditions or events that may trigger the imposition
of restricted entitlements include unscheduled inter-
ruptions or curtailments of service, force majeure
events on Paiute's system and/or the systems of upstream
pipelines (such as pipeline, compressor, or storage
facility failures), excess linepack drafting or packing,
and unexpected extreme weather conditions. An explicit
operational flow order (OFO) statement (verbal or written)
by Paiute is required to activate this section. The OFO
may be issued at any time during the Gas Day, using the
procedures set forth in Section 4.6(f) of the General
Terms and Conditions, and will be effective immediately
unless otherwise specified. The OFO may be issued for
either overrun or underrun situations and may be appli-
cable to all Shippers or to individual Shippers taking
more or less gas from the system than the quantities
scheduled for delivery to such Shippers. Paiute shall
specify in the OFO statement whether the entitlement
event is an overrun or underrun entitlement.
(2) Daily Scheduled Quantity: The quantity of gas sched-
uled pursuant to Section 4.2 and/or Section 4.6 of the
General Terms and Conditions of this tariff shall
constitute the maximum quantity that Paiute is obligated
to deliver to Shipper (Daily Scheduled Quantity).
(3) Any quantity taken by Shipper in excess of the Daily
Scheduled Quantity during an OFO period applicable to an
overrun situation shall constitute an Unauthorized Daily
Overrun. Any quantity taken by a Shipper less than the
Daily Scheduled Quantity during an OFO period applicable
to an underrun situation shall constitute an Unauthorized
Daily Underrun. An Unauthorized Daily Overrun and an
Unauthorized Daily Underrun are subject to the following
penalties: