35. PIPELINE INTEGRITY PLAN (PIP) SURCHARGE (Continued)
35.8 True-up (Continued)
recovered, through application of PIP Surcharges, costs that
are in excess of $40 million, Transporter will file to
establish a negative surcharge to return amounts collected in
excess of the final Net Qualifying Cost balance. The negative
surcharges must be designed such that they may be applied in
full by the end of the same calendar year. Such amounts
returned by Transporter may not exceed the amounts recovered by
Transporter through application of PIP Surcharges. The final
true-up calculation will additionally take into account the
difference between the estimated transportation throughput used
to set the PIP Surcharge(s) and actual transportation
throughput during the last year a surcharge is in effect.
35.9 Interest: Except as set forth in Section 35.5(b), interest
shall not be included in any charge or refund that will be
provided pursuant to the PIP tracking mechanism set forth
herein.