Gas Transmission Northwest Corp.
Third Revised Volume No. 1-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/15/2010, Docket: RP10-606-000, Status: Effective
Tenth Revised Sheet No. 27 Tenth Revised Sheet No. 27
Superseding: Ninth Revised Sheet No. 27
STATEMENT OF EFFECTIVE RATES AND CHARGES
FOR TRANSPORTATION OF NATURAL GAS
(Continued)
NEGOTIATED RATE AGREEMENTS UNDER RATE SCHEDULE ITS-1, PS-1, AND AIS-1
Explanatory Footnotes for Negotiated Rates under Rate Schedule ITS-1, PS-1,
and AIS-1
5/ This agreement is for service under GTN's Rate Schedule PS-1. The fee
charged for this service under this agreement shall be determined as follows:
Maximum Allowable Total Quantity to be Parked: 250,000 Dth
Maximum Allowable Daily Quantity to be Parked: 20,000 Dth per day (or as
otherwise agreed upon by GTN
and Sempra)
Allowable Period to Park Quantities: April 15 - April 30, 2010
Allowable Period to Withdraw Parked Quantities: January 1 - January 31, 2011
Total Charge US$ (assessed May 2010): US$302,500.00
Sempra Energy Trading Corp. ("Sempra") shall use good faith efforts to park
gas on a ratable basis, up to the Maximum Allowable Daily Quantity to be
Parked, or as otherwise mutually agreed and further subject to GTN's ability
to park such quantities at the receipt point(s) specified in Sempra's Parking
Service Agreement. In addition, Sempra shall use good faith efforts to
withdraw all gas parked on a ratable basis, plus or minus 20%, or as otherwise
mutually agreed between GTN and Sempra, and further subject to GTN's ability
to redeliver such quantities at the same point(s) the gas was parked.
Any quantities Sempra parks on GTN's system in excess of the contracted
quantity between April 15, 2010, through April 30, 2010 (the "Parking
Period"), and any quantities parked in periods other than the Parking Period,
shall be subject to GTN's maximum tariff rate or other such generally
available system-wide discounted rate under Rate Schedule PS-1.
GTN shall reimburse Sempra $0.20/Dth, up to the contracted quantity for any
difference between the actual parked quantity during the Parking Period, and
the contracted quantity, applicable to any nominated and otherwise confirmable
quantities GTN was unable to park on its system during the Parking Period,
which may be occasioned by restricted capacity, adverse inventory positions or
GTN scheduling errors. Sempra is obligated to make nominations on all
available nomination cycles during the day to be eligible for reimbursement.
Sempra shall have the right to request on subsequent days the makeup of
quantities GTN was unable to park.
GTN shall reimburse Sempra $0.20/Dth, up to the quantity actually parked, for
any quantities not withdrawn from GTN's system between January 1, 2011 and
January 31, 2011 (the "Withdrawal Period") due to GTN's inability to
accommodate a nominated and otherwise confirmable withdrawal for that
quantity during the Withdrawal Period, which may be occasioned by restricted
capacity, adverse inventory positions, or GTN scheduling errors. Sempra is
obligated to make nominations on all available nomination cycles during the
day to be eligible for reimbursement. Sempra shall have the right to request
on subsequent days the makeup of quantities GTN was unable to withdraw.
6/ Reserved