STATEMENT OF EFFECTIVE RATES AND CHARGES
FOR TRANSPORTATION OF NATURAL GAS
(Continued)
NEGOTIATED RATE AGREEMENTS UNDER RATE SCHEDULES FTS-1 AND LFS-1
Explanatory Footnotes for Negotiated Rates
under Rate Schedules FTS-1 and LFS-1
/11 The per-Dth Reservation Rate shall be determined daily and will equal [the
Gas Daily Midpoint Price (the Gas Daily Midpoint Price is the price survey
midpoint for PG&E, Malin and Stanfield, OR as published in Gas Daily for the
day of gas flow. Weekend and holiday prices will be determined using the most
recently available Gas Daily publication) for PG&E, Malin minus the Gas Daily
Midpoint Price for Stanfield, OR, minus the sum of the following]:
1) an allowance for the per-Dth cost of GTN system fuel
2) an allowance for the per-Dth cost of delivery of volumes on the GTN
System equal to the maximum delivery rate applicable under GTN's FTS-1
Tariff for the volumes transported, multiplied by the distance
transported
3) an allowance for ACA of $0.0016/Dth
The allowance for GTN System fuel shall be computed as follows:
The Gas Daily Midpoint Price for Stanfield, OR, multiplied by the
applicable fuel and line loss percentage for the actual path utilized to
transport gas.
Fuel shall be reimbursed in kind at the applicable monthly percentage as
posted on GTN's website.
On any day when the foregoing Reservation Rate calculation produces a result
less than or equal to $0.08/Dth, the Reservation Rate shall be deemed to be
$0.03/Dth. On any day when the foregoing Reservation Rate calculation produces
a result greater than $0.08/Dth, the Reservation Rate shall be deemed to be
equal to the calculated per-Dth Reservation Rate minus $0.05/Dth. To determine
the Index Rate calculation applicable to volumes not nominated or scheduled,
the Stanfield to Malin mileage will be applied to the calculation's mileage-
based components.
In addition to the Reservation Rate as calculated herein, PPM Energy shall pay
the Delivery Rate for volumes transported equal to the maximum delivery rate,
plus the ACA charge as applicable under GTN's FTS-1 Tariff. PPM Energy shall
provide fuel in kind in accordance with GTN's FTS-1 Tariff.
In the event that the indices for PG&E, Malin and/or Stanfield, OR are not
published on any given day (other than a weekend or holiday), prices will be
determined based on the last published information for such index. In the
event that the indices for PG&E, Malin and/or Stanfield, OR are not published
on at least three business days within a span of six business days, either
party may request negotiation of a replacement rate structure (a
"Renegotiation Request"). Upon such Renegotiation Request, GTN and PPM Energy
will use diligent, good faith efforts to come to a mutually agreeable
replacement rate structure. Firm Transportation Service Agreement F-10442
will terminate on the fifteenth day following a Renegotiation Request in the
event the parties do not agree on a replacement rate structure prior to such
termination.