RATE SCHEDULE TF-1
Firm Transportation (Continued)
6. SCHEDULED OVERRUN TRANSPORTATION (Continued)
For Scheduled Quantities in excess of Shipper's Transportation
Contract Demand, Shipper shall pay for the excess gas transportation on
any such day the amounts specified below:
6.1 An amount obtained as the sum of (a) and (b):
(a) An amount obtained by multiplying (i) the quantity of Dth in
excess of Transportation Contract Demand by (ii) the Maximum
Currently Effective Scheduled Overrun Transportation rate per Dth
as set forth on Sheet No. 5 of this Tariff, unless otherwise
agreed to by Shipper and Transporter.
(b) An amount obtained by multiplying (i) the quantity of Dth in
excess of Transportation Contract Demand by (ii) the sum of the
applicable GRI adjustment and the ACA component as set forth on
Sheet No. 5 of this Tariff. These charges shall be subject to
adjustment in accordance with Sections 13 and 16 of the General
Terms and Conditions.
(c) Additionally, if Shipper and Transporter have agreed to a
rate other than the Currently Effective Maximum Scheduled Overrun
Transportation rate, Shipper may, when nominating, electronically
select an option that will automatically increase (by a stated
dollar increment per dth) such rate up to the rate that will
increase the likelihood of such quantities being scheduled
pursuant to Section 12 of the General Terms and Conditions.
6.2 The fuel reimbursement provided for in Section 7 of this Rate
Schedule.