Northwest Pipeline Corporation G P
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/20/2009, Docket: RP09-227-000, Status: Effective
Second Revised Sheet No. 20 Second Revised Sheet No. 20
Superseding: First Revised Sheet No. 20
RATE SCHEDULE TF-1
Firm Transportation
(Continued)
3. MONTHLY RATE(S) (Continued)
3.6 Charges for Capacity Release Service: The rates for capacity
release service are set forth in Sheet No. 5. See Section 22 of the
General Terms and Conditions for information about rates for capacity
release service, including information about acceptable bids. In the
event of a base tariff maximum and/or minimum rate change, wherein the
Replacement Shipper has not agreed to pay the maximum base tariff rate
or a percentage of the maximum base tariff rate (as it may change from
time-to-time), the Replacement Shipper will be obligated to pay:
(a) for capacity release transactions that are subject to the
maximum base tariff rate pursuant to FERC regulations: the lesser
of the awarded bid rate and the new maximum base tariff rate
unless the awarded bid rate is less than the new minimum rate, in
which case the new minimum rate will apply for the remaining term
of the release.
(b) for capacity release transactions that are not subject to the
maximum base tariff rate pursuant to FERC regulations: the greater
of the minimum base tariff rate and the awarded bid rate for the
remaining term of the release.
3.7 Negotiated Rates: Notwithstanding the general provisions of this
Section 3, if Transporter and Shipper mutually agree to Negotiated Rates
for service hereunder, such Negotiated Rates will apply in lieu of the
otherwise applicable rates identified in this Section 3.
3.8 Facility Reimbursement: If Transporter and Shipper enter into a
facilities agreement pursuant to Section 21 of the General Terms and
Conditions for Transporter to construct receipt or delivery facilities
necessary to provide service under this Rate Schedule and for Shipper to
reimburse the associated costs by paying a facility reimbursement
charge, the facility reimbursement charge will be set forth on Exhibit C